Website project Gantt chart template
A typical marketing website on a CMS takes about nine weeks from kickoff to go-live, plus a week of fixes after launch. This template lays that out in four phases (discovery, design, build and launch) and flags the three jobs the client owns: supplying content, reviewing the design and user acceptance testing. Those three are where most website timelines slip.
- Discovery
- Kickoff workshop
- Stakeholder interviews
- Sitemap & content plan
- Content & brand assets suppliedclient
- Discovery sign-off
- Design
- Wireframes
- Visual design
- Design review & feedbackclient
- Design approved
- Build
- Front-end development
- CMS setup & integrations
- Content entry
- Launch
- QA & browser testing
- User acceptance testingclient
- Go live 🚀
- Post-launch fixes
This is the actual template. Durations count working days; weekends are skipped. Drag any bar to reshape it once it’s open.
When to use it
- You’re quoting a new site and the proposal needs a timeline that holds the client to their dates as well as you to yours.
- Design, development and whoever writes the copy work in different places, and nobody can see the whole schedule.
- On the last project the content turned up a week before launch. This time its deadline goes on the plan in week two.
- You’re building in-house and marketing keeps asking when they can start loading pages.
What’s in it
- 01
Discovery
Kickoff, stakeholder interviews, then the sitemap and content plan, closing at Discovery sign-off around the end of week two. The client’s content and brand assets bar starts in week two and runs on into design. Ask for logo files, photography and existing copy at kickoff; new page copy can follow once the sitemap says which pages exist.
- 02
Design
Wireframes, then visual design, then a one-week client review before Design approved at about week six. Agree the number of feedback rounds in the contract as well as on the chart. Open-ended rounds are how a three-week design phase turns into six.
- 03
Build
Front-end development runs about two and a half weeks, with CMS setup and integrations alongside. Content entry starts about a week and a half in, once page templates exist, and it’s slower than anyone quotes: images need resizing, alt text needs writing, and copy pasted from Word brings its formatting along. If the client is loading their own content, flag that bar as a client task too.
- 04
Launch
QA and browser testing, the client’s user acceptance testing, then Go live at about week nine and a week of post-launch fixes. Put the dull checks on the list before launch day: DNS and SSL, form notifications reaching a monitored inbox, analytics firing, and redirects if an old site lived on the same domain.
Adapting it to your project
Put the content deadline in the contract
Ask for access in week one
Save an iteration at design approval
Add shutdowns before you quote
Questions
How long does it take to build a website?
About nine to ten weeks for a marketing site on a CMS, which is what this template assumes. Small brochure sites can launch in six to eight weeks; e-commerce, custom integrations or large content migrations often take four to six months. The biggest variable is how quickly content and feedback come back from the client.
What should a website project timeline include?
Discovery (kickoff, interviews, sitemap and content plan), design (wireframes, visual design, client review), build (development, CMS setup, content entry), launch (QA, user acceptance testing, go-live) and a short window for fixes afterwards. Milestones at discovery sign-off, design approval and go-live give the client three clear decision points.
Can the client follow the plan without logging in?
Yes. Send them a view-only share link; it always shows the current dates, and bars flagged as client tasks carry the client’s logo, so they can see which jobs are theirs. For a proposal, export it as a one-page PDF instead.